Public Works continues with the repair of streets and avenues of Mazatlan

861

This Monday, a stretch of street was re-carpeted and the patching program was followed up 


Mazatlán, Sinaloa.- Personnel from the Public Works Department continue to monitor the repair of streets and avenues in Mazatlán, through different actions that were carried out this Monday. 


With the operation of the pothole machine acquired by the Municipal Government, the problem of various sections with potholes on Enrique Pérez Arce and Libramiento II avenues was addressed.


With the machinery, and four workers from the operational area unit, 3 cubic meters of asphalt were applied to cover an area of ​​30 square meters of potholes in both roads. 


In addition, resurfacing work was carried out on Walamo avenue, in the San Joaquín subdivision; 48 cubic meters of asphalt were used to cover 1,300 square meters.


With a patching crew, a motor grader, a water tank truck and 4 dump trucks, the staff carried out the work at noon this Monday, leaving the asphalt tape with better quality for the use of drivers who drive through the zone.

The Mazatlan Post